Overview |
BOM routing sequences/steps represent specific actions that need to be executed for manufacturing, test, and/or assembly purposes.
BOM routings can contain an unlimited number of sequences.
Each sequence can include items from the bill of material that are used/consumed for that particular step.
Sequences/Steps can be grouped under "Operations" for intuitive sectioning, easy navigation, and hierarchical representation.
The Operation usually defines a specific manufacturing, assembly, or test stage.
Routings can contain an unlimited number of Operations.
Routing structure: |
• Operation 1 |
|
» Sequence 1 |
|
... |
|
» Sequence N |
• Operation 2 |
|
» Sequence 1 |
|
... |
|
» Sequence N |
... |
• Operation N |
|
» Sequence 1 |
|
... |
|
» Sequence N |
|
|
Operations Page/List |
Top |
|
To modify Routing operations, click the Operations tab from the Routing form navigation bar.
The Operations page will list all operations assigned to the Routing.
For users with editing permissions, the toolbar will contain functions for adding and editing operations.
You can also copy operations from a different BOM and/or revision.
Users with editing permissions will also have an Actions column for modifying individual operations.
Each operation will contain a hyperlink in the Name column.
Clicking the hyperlink will open the Sequences page on that operation.
|
|
Adding Operations |
Top |
|
To add an operation, click the Add Operation toolbar button.
This will display the Add Operation dialog box.
From the Add Operation dialog, you can specify an operation Prefix, Number, and Description.
If custom fields are enabled (Omnify Administrator), the field options will appear in the dialog box.
To add the operation, click either the Add or Apply buttons.
|
|
Removing Operations |
Top |
|
To remove an operation, click the Remove icon in the Actions column of the Operation list.
You will be asked to verify the removal.
|
|
Editing Operations |
Top |
|
To edit an operation, click the Edit icon in the Actions column of the Operation list.
The Edit Operation dialog will appear and the data from the selected operation will be populated.
To edit, modify the desired properties and then click the Update button.
|
|
Group Editing Operations |
Top |
|
You can edit/modify 2 or more operations by clicking the Edit All toolbar button.
This will present edit boxes/options for all operations.
Once all changes have been made, click the Save Operations button.
|
|
Ordering Operations |
Top |
|
You can modify the operation order by using the Up and Down icons in the Actions column of the Operation list.
|
|
Copying Routings |
Top |
|
To copy the Routing from one BOM and/or revision to another, click the Copy/Apply Routing toolbar button.
This will present the Copy Existing Routing dialog.
From this dialog box, you will be able to specify (or browse for) and existing BOM item and rev.
You will have the option of which routing items you wish to copy.
Once the BOM part number, revision, and options have been specified, click the Copy Routing button to apply the routing data to the current BOM.
|